Wednesday, June 3, 2009

I've Been Slacking



I've been slacking. I was trying to do blog updates regularly as progress occurred, but kinda fell off the radar for a bit. Let's just say building a house keeps you busy even when you are doing almost none of the work involved. How about some pictures so you can see the progress?



This is Isaac's room about 10 days ago. 









This is Kaden & Xander's room about 2 days ago. I forgot to take a picture of Isaac's from the same angle as before but their rooms are mirror images of each other so you get the idea.







This is the fireplace before painting.









And this is the fireplace after painting.









This is Sunshine's room/closet before painting.












We wanted her room to be bright and cheerful so we painting it after the painter was done with the rest of the house.

Yellow wall is west, pink wall is north






Green wall is east, purple wall is south













Purple wall is south, yellow wall is west









Pink wall is north, green wall is east.









This is looking into the master bathroom before paint












This is looking in after paint and after tile (but before grout).












This is the upstairs hall before paint.













This is after paint.









This is the dining room looking east before paint and most of the trim.








This is the dining room looking west after paint and trim.








Sorry about all the pictures. :) 

The tile should be done by the time we go up today along with the cabinets and countertops so hopefully more pictures will come later today of tomorrow. They are supposed to start on the exterior next week. We are less than a month and a half away from the scheduled completion date. :)

Sunday, May 17, 2009

Camping With the Boys

On Friday we went camping up by Morgan, Utah. We had a really great time and enjoyed yummy food. While camping is not my favorite thing, the boys seemed to love it. I didn't get a ton of sleep, but in the end it didn't matter because memories last forever, you can always get sleep another day.


The boys in the car on our way to go camping.








Xander and Kaden gathering some sticks for the camp fire.








Isaac helping with dinner. Chicken Cordon Bleu and potatoes cooked in dutch ovens. Yummy!!!








Kaden using a hatchet to cut a branch.












Making s'mores in the campfire.









Happy boys at the top of the hill after our hike.

Rock


Tomorrow begins the finish work. The trim and doors are inside the house waiting for installation. We meet with the finish carpenter tomorrow to design our mantle and to go over the trim styles. Things are moving along!!!

On Friday they installed the rock onto our front porch pillars. Can't wait to see it with all our other outdoor elements.



Thursday, May 14, 2009

Moving Along



Things are getting done everyday. The driveway now extends from the front of the garage to the front edge of the front porch. There is approximately another 25 feet to the street, but the trees in front of the house need to be removed first so I don't know exactly when they will pour the rest.

The sheetrock is almost done and we meet with the "finish" carpenter on Monday. He will install all the mouldings, the railings on the interior, the closet organizers, and the fireplace mantle. Then it's on to paint, flooring, cabinets, and the rest of the house.


The front door has the dentil shelf installed. We still need to pick out the stain color.











This is the back of the house, obviously. :)









This is the north side of the house. They finally fixed the far window well which they drove a trailer over about a month ago.







Looking at the front of the house.









We decided on our kitchen sink today. We decided to go with a triple bowl sink. The garbage disposal will be installed in the middle sink so you can rinse your dishes and get the food off without having to empty one of teh sinks. We lose a small amount of counter space as a result but it will be worth it and we found a kilelr deal online for this sink.

Saturday, May 9, 2009

Sheetrock




Ahh the sweet smell of sheetrock mud. Lots of progress in the last two days at the house. Hopefully we can keep this pace going and get completed!!!! Yesterday they pourded about 15 feet of concrete in front of the garage and installed the drywall in the garage. It still needs to be taped and mudded in there but things are coming along. 


This is the kitchen/dining room area. As you can see yesterday was a very productive day!!! All the sheetrock is installed in the entire house and they are working today to mud/tape everything. I think they will be done quicker than originally anticipated; hopefully, we can get started on the next phase sooner as well.





This is the master bedroom looking towards the master bathroom entrance.








This is the living room.









They also poured the back patio concrete yesterday as well. The roof has been installed on both the garage and the house. They also installed the gas meter yesterday as well. It's kinda cool to see a meter with all the arrows pointing to zero.

Friday, May 8, 2009

Insulation




The insulation has been installed on all the exterior walls on every floor and in a few ceiling locations. The house was "filled" with sheetrock yesterday afternoon (prompting an upstairs window to be removed to get the panels up there) and installation of them begins today. They have set up forms in front of the garage and where the back porch will sit and it appears they may pour some concrete today. The shingles are on top of the garage and the house and I think they will finish the roof up soon. The crews are very busy and things are moving along. I'm hopeful for an early completion but as of right now it looks like the middle of July will be when we are completed.

Tuesday, May 5, 2009

Doors and Windows



Almost all the windows are in and the exterior doors have been installed. The heating, plumbing, and electrical (except for a few missing items) have been installed. Insulation begins tomorrow and sheetrock is scheduled to be installed on Friday. It is looking more and more like a house everyday. :)


This is a close up picture of the front door. It is supposed to have a dentil shelf below the six windows, not sure why it doesn't yet but I have an e-mail sent to find out why).









This is the main electrical panel in the laundry room. 












This is the furnace in the laundry room. The gas has been run to it and the fireplace upstairs and the heating ducts appear to all be installed.











This is the back of the house with the back door installed.









This is the garage. Alot of progress in the last two days here as well. The roof sheathing is installed, the door, window, and power meter panel as well.







This is the north side of the house. The basement windows have not been installed but with sheetrock a few days away I anticipate they will probably be there by the next time I visit.

On a side note, Blogspot is acting really weird lately and it has been a pain to post things!!!