Sunday, May 17, 2009

Camping With the Boys

On Friday we went camping up by Morgan, Utah. We had a really great time and enjoyed yummy food. While camping is not my favorite thing, the boys seemed to love it. I didn't get a ton of sleep, but in the end it didn't matter because memories last forever, you can always get sleep another day.


The boys in the car on our way to go camping.








Xander and Kaden gathering some sticks for the camp fire.








Isaac helping with dinner. Chicken Cordon Bleu and potatoes cooked in dutch ovens. Yummy!!!








Kaden using a hatchet to cut a branch.












Making s'mores in the campfire.









Happy boys at the top of the hill after our hike.

Rock


Tomorrow begins the finish work. The trim and doors are inside the house waiting for installation. We meet with the finish carpenter tomorrow to design our mantle and to go over the trim styles. Things are moving along!!!

On Friday they installed the rock onto our front porch pillars. Can't wait to see it with all our other outdoor elements.



Thursday, May 14, 2009

Moving Along



Things are getting done everyday. The driveway now extends from the front of the garage to the front edge of the front porch. There is approximately another 25 feet to the street, but the trees in front of the house need to be removed first so I don't know exactly when they will pour the rest.

The sheetrock is almost done and we meet with the "finish" carpenter on Monday. He will install all the mouldings, the railings on the interior, the closet organizers, and the fireplace mantle. Then it's on to paint, flooring, cabinets, and the rest of the house.


The front door has the dentil shelf installed. We still need to pick out the stain color.











This is the back of the house, obviously. :)









This is the north side of the house. They finally fixed the far window well which they drove a trailer over about a month ago.







Looking at the front of the house.









We decided on our kitchen sink today. We decided to go with a triple bowl sink. The garbage disposal will be installed in the middle sink so you can rinse your dishes and get the food off without having to empty one of teh sinks. We lose a small amount of counter space as a result but it will be worth it and we found a kilelr deal online for this sink.

Saturday, May 9, 2009

Sheetrock




Ahh the sweet smell of sheetrock mud. Lots of progress in the last two days at the house. Hopefully we can keep this pace going and get completed!!!! Yesterday they pourded about 15 feet of concrete in front of the garage and installed the drywall in the garage. It still needs to be taped and mudded in there but things are coming along. 


This is the kitchen/dining room area. As you can see yesterday was a very productive day!!! All the sheetrock is installed in the entire house and they are working today to mud/tape everything. I think they will be done quicker than originally anticipated; hopefully, we can get started on the next phase sooner as well.





This is the master bedroom looking towards the master bathroom entrance.








This is the living room.









They also poured the back patio concrete yesterday as well. The roof has been installed on both the garage and the house. They also installed the gas meter yesterday as well. It's kinda cool to see a meter with all the arrows pointing to zero.

Friday, May 8, 2009

Insulation




The insulation has been installed on all the exterior walls on every floor and in a few ceiling locations. The house was "filled" with sheetrock yesterday afternoon (prompting an upstairs window to be removed to get the panels up there) and installation of them begins today. They have set up forms in front of the garage and where the back porch will sit and it appears they may pour some concrete today. The shingles are on top of the garage and the house and I think they will finish the roof up soon. The crews are very busy and things are moving along. I'm hopeful for an early completion but as of right now it looks like the middle of July will be when we are completed.

Tuesday, May 5, 2009

Doors and Windows



Almost all the windows are in and the exterior doors have been installed. The heating, plumbing, and electrical (except for a few missing items) have been installed. Insulation begins tomorrow and sheetrock is scheduled to be installed on Friday. It is looking more and more like a house everyday. :)


This is a close up picture of the front door. It is supposed to have a dentil shelf below the six windows, not sure why it doesn't yet but I have an e-mail sent to find out why).









This is the main electrical panel in the laundry room. 












This is the furnace in the laundry room. The gas has been run to it and the fireplace upstairs and the heating ducts appear to all be installed.











This is the back of the house with the back door installed.









This is the garage. Alot of progress in the last two days here as well. The roof sheathing is installed, the door, window, and power meter panel as well.







This is the north side of the house. The basement windows have not been installed but with sheetrock a few days away I anticipate they will probably be there by the next time I visit.

On a side note, Blogspot is acting really weird lately and it has been a pain to post things!!!

Sunday, May 3, 2009

Kids Pick Rooms



Since it was finally safe to allow the kids to go upstairs as the windows are now in on the 2nd floor and the rooms are defined we decided to allow the kids to pick their bedrooms.


Kaden and Xander did not get to really pick as they were left with the last room available (they will each be getting their own rooms once the basement is done). Here they are standing in front of their windows. Their room is the south facing room. 








We allowed Isaac to pick his bedroom first since he will be staying on the 2nd floor once the basement is finished. He chose the bedroom facing north. He is very excited!!









Sunshine picked her bedroom second. It is a perfect fit for her. It faces to the east and I think the windows were what drew her to this room. It also has the biggest closet which is important when you are the princess. :)








I took a tape measure and it appears each bedroom is approximately the same square footage. The boys all picked rooms that will have built in bookshelves, perfect for reading!!!


This is the south side of the house. The windows on the second floor belong to Kaden and Xander's room.










This is the back of the house. The three small windows are in the upstairs bathroom.








This is the north side of the house. The windows on the second floor belong to Isaac.








This is the laundry room.












This is looking at the master bedroom closet.












This is the jetted tub in the master bathroom









This is standing in the dining room looking across the main floor towards the master bathroom.








This is the fireplace. There is enough room above it for a 52" flatsceen TV. 











This is Kaden and Xander's closet.









This is the upstairs bathroom looking at the bathtub.












This is Isaac's closet.









This is Sunshine's closet.










They will finish up HVAC, plumbing, and electrical over the next few days. Insualtion installation is scheduled to begin on Wednesday and sheetrock will begin being hung on Friday.